      1 - Opening Shots 2 3 4
5 6 7 8 9 10 11 - Clearing
12 13 - Permits Issued Work Starts 14 -Ground Breaking 15 - Footers 16 17 - Forms Setup 18 -Forms Setup
19 20 21 - Foundation Poured 22 23 - Green Walls forms coming off 24 - Forms off 25 - Almost ready for Steel
26 27 28 29 30  

December 2006
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
          1 - Foundation 2
3 4 5 - 1st Deck Start 6 - Steel Set 7 - Truss & Floor Heating 8 - First Walls 9
10 11 - More Walls 12 - Walls 13 14 - Walls & Dirt 15 - Garage & 2nd Deck 16
17 - Kids Visit Site 18 -Walls are climbing 19 - Framing 2nd floor 20 21 - Putting on Roof 22 23 - Under Roof 2nd floor ready
24 25 26 27 - Framing out 2nd Floor 28 - Finishing Roof 29 - Garage Floor + Roof Install 30
31            

January 2007
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
  1 - Staring the Year 2 3 4 - House Wrapped 5 6
7 8 9- 1st Floor Frame Out 10 - Frame out 11 - Windows & Doors 12 13
14 15 16 -Septic & HVAC Start 17 - Septic & HVAC 18 19-Fireplace 20 - Ast. New stuff
21 22 - Trim, HVAC, Wells 23 - Geothermal Wells and Septic 24 - Busy Day on Site 25 26 - Doors & Trim & Plumbing 27
28 - Great room shots 29 30 31      

February 2007
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
      1 2 3 - Wiring
4 - Wiring the Data Lines 5 6 - Inside shots 7 8 9 - Geothermal Well finished 10 - TV - Wiring
11 - A/V & Net wiring 12 - COLD & Snow 13- COLD & Snow 14 - COLD & Snow 15 - WSSC Insp 16 - Insulate (Early) 17 - Wkly Shots
18 - Network Punch down - 2 Cold 19 - Stone Arrives 20 - Framing Insp & Stone Work 21 - Inspection & Siding + Stone 22 - Stonework & Siding 23 - Drywall Starts + Plugs 24 - Drywall work and exterior shots
25 26 - Drywall Finish 27 - Stone Work 28 - Stone Work      

 

March 2007
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
      1 - Exterior Finished 2 - Drywall

3 - Drywall sand done

4 - Exterior Stone Work 5 - Fireplace Mantle & Exterior 6 - Exterior Shots Fireplace Stone & Garage Doors 7 - Doors, Fileplace, exterior shots 8 - Doors & Trim 9 - Trim 10 - Road Trip to PA & Back
11 12 13 - Trimmed Out 14 15 16 - Primed 17
18 19 20 - Paint Start 21 22 - White Paint Coat 23 24
25 - Color coat & Grading 26 27- Kit Cab 28 - Kitchen Cabs 29 - Stove 30- Kitchen Cabs, Stove, Deck Sample, Outside 31 - Granite Hunting

 

April 2007
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
1 2 - Ceramics 3 - Granite 4 - Rails & Tile 5 - ELECTRICITY & HEAT 6 7
8 9 - Tile & Deck 10 - Tile, Shelve, Mirrors, Locks, etc 11 - Counter tops & Trim 12 13 - Eletrical Fixtures 14
15 16 - Paint, Lights 17 - Plumbing, Driveay, Wood Floors 18 - Wood Floors 19 - Wood Floors 20 - Wood Floors 21
22 23 - Electric 24 - Trimming the House 25 - Alarm, 26 - Deck is on 27 - Paint 28 - Spring and almost ready
29 30 - Stove & Carpet going down          

 

May 2007
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
    1 - Gradeing 2 - Preping Driveway 3 4 - Paving Driveway 5 Upstairs Railing
6 7 8 - Sun Tunnel Arives 9 10 - Kitchen & DR & Fireplace 11 - Jack Explores 12 - Landscaper
13 14 15 - U & O 16 - Front Posts and Video Tour 17- Sun Tunnel & Walk Through 18 19
20 21 22 23 24 - Pat in Kitchen 25 - Move In 26 - Refrig Due
27 - Guest Arive 28 29 30 31    

 

 

 